System Schedule

System Initial design and approval - July 2007
Supply Contract - NEC signed Sept 2007
Marine Route survey - Sept. to Nov. 2007
Supply Contract - IT Telecom Marine Dec. 2007
FCC 214 Landiing License - Dec. 2007
US COE, USFS, AK DNR and other local permits and
ROW's - current being applied for Start of Marine
Construction - June 2008
Completed project - October 2008